Weather is playing a role in efforts to complete paving projects in Fort Frances.
Paving of Central Avenue was planned for last week, but Operations and Facilities Manager Doug Brown says temperatures weren't conducive for laying asphalt.
"You have to a temperature of 7 C and rising," says Brown.
Brown says crews are now looking to the end of this week to pave the area, weather permitting.